This report provides a comparison of the budgeted hours or values versus either:
You can generate the report for a selection of clients.
The report setup window opens in the main desktop. Specify the relevant report options (see below).
Select Actual Time & Expenses or Planned Time, as appropriate.
Option | Description |
---|---|
From/To | The span of time the report will cover. |
Include... |
Select one of these radio buttons to specify whether budgeted hours will be compared to:
|
Details to Show: Employees per position | Select this checkbox if you want the report to include the number of employees with budgeted hours in each position. |
Details to Show: Values |
Select this checkbox to break down the report by value as well as by hours (or days). This option is available only if you have been granted the Show Charge-Out Value of Time permission in your user profile. |
Details to Show: Time in days | Select this checkbox to break down the report by days rather than by hours. For example, one and a half days is shown as 1.5. |
Details to Show: Include Our Costs | This checkbox enables you to include employee cost values in the report. |
Details to Show: Include Budget / Var Hours | This checkbox enables you to include budgeted hours in the report. |
Report Filters tab: Client | This panel enables you to include specific clients in the report. |
Report Filters tab: Employee | This panel enables you to include specific employees in the report. |
Grouping tab: Project Analysis Grouping | This panel enables you to use project analysis groupings to specify which projects will be included in the report. |
Column | Description |
---|---|
Position | The report breaks down hours by position. |
Activity/Expense | This column lists the activities and expenses associated with the relevant position in the relevant project. |
[Project Name] | This column identifies the project associated with the relevant list of activities and expenses. |
Bud |
This column shows the budgeted hours or value associated with each activity and expense. It also provides relevant sub-totals. |
Act /Plan | This column shows either the actual hours or value associated with each activity and expense, or the planned hours or value associated with each one (depending on whether the Show Value report option is selected). |
Var |
This column shows the hours or value derived by one of the following calculations (depending on whether the Show Value report option is selected):
|
Active Budget | This column indicates whether the relevant budget is active. |